QuestionOne work was done by team 1 in 10 days and team 2 in 15 days. If we cooperate, how many days will the work be done?

Studdy Solution
Determine the total time needed to complete the work using the combined work rate. Total time=1 work16 work/day=6 days \text{Total time} = \frac{1 \text{ work}}{\frac{1}{6} \text{ work/day}} = 6 \text{ days}
Solution: The work will be completed in 6 days when both teams cooperate.