QuestionRefer to the project described by the project digraph shown on the right Complete parts (a) and (b) below. (a) Find the critical path for the project. Choose the correct answer below. A. START, B, E, I, K, END B. START, C, G, K, END C. START, B, F, I, K, END D. START, A, E, I, K, END

Studdy Solution
Determine the path with the longest duration. This path is the critical path.
The longest duration is 37, which corresponds to the path: - START, B, E, I, K, END
The critical path for the project is:
START, B, E, I, K, END \boxed{\text{START, B, E, I, K, END}}